Specialistic support for geomechanical and structural design of tunnels (Caprazoppa, Monte Grosso, Castellari, Croce, Pineland, Alassio; 47 km of tunnels, 37 km excavated by TBM) and of Alassio underground station.
Autostrada Bre.Be.Mi. New motorway between the two cities of Milan and Brescia: main axis and link to Brescia's belt-way
Project Phase
DD
Date
2009 - 2011
Amount
800M
Our Client
IMPRESA PIZZAROTTI SpA
Main Client
CONSORZIO B.B.M.
Job Description
Geotechnical design to address all relevant problems along the path: embankments, cuttings, viaducts, artificial tunnels below the water table.Design of temporary works for foundations of the Adda and Oglio viaducts. Detailed geological and geomorphological design at the main works of art. General review of seismic and hydrogeological design after supplementary site investigation.